Quantity/Term, Estimated Value and Estimated Quarter for each procurement are approximate indicators only. Factors such as availability, project increase or decrease may impact the actual requirement.
Vendors interested in registering with the United Nations Procurement Division Supplier Database must submit an application along with detailed information demonstrating experience and qualifications in provision of the relevant commodities/services.
| Commodity |
Description |
Qty/Term |
Est. Value |
Est. Qtr |
| AirOps |
Training for Aviation and AMISOM Staff |
12 months |
$ 250,000.00 |
3 |
|
Aviation X-ray, and security equipment |
12 months |
$ 403,400.00 |
3 |
|
Fire Trucks services |
12 months |
$ 490,000.00 |
3 |
|
Aviation Safety and Security services in Somalia |
12 months |
$ 600,000.00 |
3 |
|
Medical Evacuation Services |
12 months |
$ 3,000,000.00 |
4 |
|
Airport Services Somalia |
12 months |
$ 5,000,000.00 |
3 |
| CITS |
GIS Professional Workstation (Class B) |
4 |
$ 30,000.00 |
1-2 |
|
Video Conference Terminal, Desktop |
10 |
$ 34,500.00 |
1-2 |
|
Digital Sender |
11 |
$ 38,000.00 |
1-2 |
|
INMARSAT Terminals |
12 |
$ 40,800.00 |
1-4 |
|
Satellite Transceiver C Band |
2 |
$ 42,300.00 |
1-2 |
|
Phnuematic Antenna Mast |
4 |
$ 46,000.00 |
1-2 |
|
UPS, Three Phase 10 KVA |
10 |
$ 46,000.00 |
1-2 |
|
Centralised Data Storage, retrieval and maintenance Support per email account |
538 |
$ 46,070.00 |
1-4 |
|
Dedicated Fractional E1connectivity UNLB |
12 |
$ 48,000.00 |
1-4 |
|
Leased Line/Fiber (Nairobi-Mombasa) |
16 |
$ 48,000.00 |
1-4 |
|
Digital Rural Telephone Links with high Speed Data |
3 |
$ 48,300.00 |
1-2 |
|
Handheld Radio, VHF |
120 |
$ 48,300.00 |
1-2 |
|
Server Rack |
8 |
$ 50,800.00 |
1-2 |
|
GIS (Archis Licenses, Google Earth) |
12 |
$ 51,090.00 |
1-4 |
|
Communications Shelter( Large Size) |
5 |
$ 51,800.00 |
1-2 |
|
UNLB leased lines /Internet Access |
12 |
$ 58,740.00 |
1-4 |
|
Locally used lines |
12 |
$ 60,000.00 |
1-4 |
|
Communications Shelter( Medium Size) |
10 |
$ 69,000.00 |
1-2 |
|
Network Switch-Medium |
5 |
$ 71,900.00 |
1-2 |
|
Direct NY Extension |
12 |
$ 72,000.00 |
1-4 |
|
Telephone Exchange Small |
2 |
$ 92,000.00 |
1-2 |
|
UPS, 3KVA |
150 |
$ 106,000.00 |
1-2 |
|
Network Router- Low |
6 |
$ 110,000.00 |
1-2 |
|
Satellite phone usage |
12 |
$ 118,800.00 |
1-4 |
|
Network Printer- Midium |
30 |
$ 120,660.00 |
1-2 |
|
Charges for Cellular phones |
|
$ 124,800.00 |
1-4 |
|
UNON Usage charges per extension |
1 |
$ 138,000.00 |
1-4 |
|
Server -Low |
20 |
$ 138,000.00 |
1-2 |
|
Server High End |
5 |
$ 143,800.00 |
1-2 |
|
Black Berry charges |
12 |
$ 147,000.00 |
1-4 |
|
GIS Server High-end |
4 |
$ 170,800.00 |
1-2 |
|
Network Switch-Low |
50 |
$ 172,500.00 |
1-2 |
|
Laptops |
150 |
$ 180,000.00 |
1-2 |
|
Centralised IT Services per PC/Laptop |
748 |
$ 180,480.00 |
1-4 |
|
Entrprise Licenses per PC/Laptop |
12 |
$ 232,500.00 |
1-4 |
|
Disk Library Backup System-High |
1 |
$ 287,500.00 |
1-2 |
|
Cisco SmartNet Coverage |
1 |
$ 291,520.00 |
1-4 |
|
Digital Microwave Links |
5 |
$ 345,000.00 |
1-2 |
|
Satellite Map Acquisition - High Resolution-GIS |
100 |
$ 350,000.00 |
1-4 |
|
UNOPS In-Theatre ICT Support To AMISON |
12 |
$ 450,000.00 |
1-4 |
|
IT and GIS Spare parts & Supplies |
Multiple |
$ 464,968.00 |
1-4 |
|
Trigyn Consultant- Nairobi and Mombasa |
12 |
$ 500,000.00 |
1-4 |
|
Containerized Data Centre |
1 |
$ 517,500.00 |
1-2 |
|
Contractual Communications Services Support- Nairobi & Mombasa (Trigyn) |
12 |
$ 600,000.00 |
1-4 |
|
Communications Equipment Spare Parts |
Multiple |
$ 605,040.00 |
1-4 |
|
Wireless LAN Kit |
15 |
$ 655,500.00 |
1-2 |
|
Satellite transponder lease |
12 |
$ 669,600.00 |
1-4 |
|
Internet Via Satellite (GSI) |
8 |
$ 1,367,280.00 |
1-4 |
|
Contractual Communications Services Support-Mogadishu |
12 |
$ 1,500,000.00 |
1-4 |
|
Part of CITS for Public Information |
1 |
$ 7,573,700.00 |
1-4 |
| Engineering |
Lighting arrestor |
6 |
$ 35,000.00 |
4 |
|
Iron Picket ( 6') |
20000 |
$ 39,790.00 |
4 |
|
Company scale waste septic system |
3 |
$ 42,000.00 |
4 |
|
Tools kit -Generators |
10 |
$ 43,000.00 |
4 |
|
Tools kit -Plumber |
5 |
$ 51,000.00 |
4 |
|
Tools kit -Electrician |
10 |
$ 57,000.00 |
4 |
|
Tools kit -HVAC |
5 |
$ 60,000.00 |
4 |
|
Boom gates |
11 |
$ 63,250.00 |
1 |
|
Module II (Water Desalination Unit) (2,500 liter/hr) |
2 |
$ 67,000.00 |
4 |
|
Lift station module II |
6 |
$ 75,000.00 |
4 |
|
5 KVA Generators |
16 |
$ 95,680.00 |
4 |
|
Electrical fixtures and accessories |
3 |
$ 104,000.00 |
4 |
|
Electrical wire |
2 |
$ 115,000.00 |
4 |
|
Tools kit -Carpenter |
10 |
$ 129,000.00 |
4 |
|
Water distribution station system |
3 |
$ 138,000.00 |
4 |
|
Concertina wire |
7500 |
$ 212,347.50 |
4 |
|
Module I (Basic Water Treatment plant (5,000 liter/hr) |
6 |
$ 258,000.00 |
4 |
|
Personnel bunker |
20 |
$ 300,000.00 |
1 |
|
20' sea worthy container used |
110 |
$ 316,250.00 |
4 |
|
Air conditioner |
560 |
$ 328,000.00 |
4 |
|
Tansit camp at Mombasa |
|
$ 385,000.00 |
1 |
|
Slding gates |
10 |
$ 400,000.00 |
1 |
|
Waste water treatment plant module III |
6 |
$ 438,000.00 |
4 |
|
Sand bags |
1000000 |
$ 483,000.00 |
4 |
|
20-125 KVA Generators |
19 |
$ 546,250.00 |
4 |
|
Concertina wire fencing fencing |
5000 |
$ 600,000.00 |
1 |
|
Warehouse |
5 |
$ 700,000.00 |
1 |
|
Hesco bastion Type MIL 2G (.061x0.61x1.22 meter) |
6100 |
$ 779,436.65 |
4 |
|
Construction of bore well |
6 |
$ 800,000.00 |
1 |
|
High security fencing |
6000 |
$ 1,000,000.00 |
1 |
|
Hesco bastion perimeter wall |
80000 |
$ 1,000,000.00 |
1 |
|
Provision of other defense and jersy barrier |
|
$ 1,000,000.00 |
1 |
|
Water storage and water distribution works |
|
$ 1,250,000.00 |
1 |
|
Provision of lightings |
|
$ 1,250,000.00 |
1 |
|
Construction of permanent kitchen and ablutionsfor 2x850 men battallion |
|
$ 1,500,000.00 |
1 |
|
Corrugated steel water tanks 100,000 liters capacity |
20 |
$ 1,725,000.00 |
4 |
|
waste management system |
|
$ 1,750,000.00 |
1 |
|
Construction of hard stand and gravel road |
|
$ 1,800,000.00 |
1 |
|
Misc services |
|
$ 3,000,000.00 |
1 |
|
Construction of 1x850 prefab accomodations |
|
$ 4,000,000.00 |
1 |
|
Power house construction and power distribution works |
|
$ 4,750,000.00 |
1 |
|
Hesco bastion Type MIL 3G (1x1xx5 meter) |
10100 |
$ 6,452,713.25 |
4 |
|
Construction of 2x850 men battalion permenent accomodation (local construction) |
$10,000,000.00 |
1 |
| Medical |
Pesticides |
quarterly |
$ 30,000.00 |
1-4 |
|
Equipment |
annually |
$ 50,000.00 |
|
|
Blood / blood products |
monthly |
$ 78,300.00 |
monthly |
|
Laboratory consumables |
quarterly |
$ 300,000.00 |
1-4 |
|
Radiology consumables |
quarterly |
$ 300,000.00 |
1-4 |
|
Medical Consumables |
quarterly |
$ 436,000.00 |
1-4 |
|
Drugs |
quarterly |
$ 477,000.00 |
3,4 |
|
Medical Services - CMK |
annually |
$ 4,140,400.00 |
monthly |
| MovCon |
Travel on emplacement, rotation and repatriation (UNP) |
bi-annual |
$ 270,800.00 |
TBD |
|
Travel on emplacement, rotation and repatriation (Cont) |
bi-annual |
$ 3,161,050.00 |
TBD |
|
Freight and deployment of contingent-owned equipment |
as needed |
$ 3,950,400.00 |
TBD |
|
Third Party Logistics Contract |
annual |
$ 8,407,155.00 |
3 |
| Supply Rations |
Stationary & Office Supplies |
12 Months |
$ 87,000.00 |
|
|
244112 - Mineral Waters in Bottles (Portable Drinking Water) |
12 Months |
$ 144,538.00 |
3 |
|
333110 - Petrol |
12 Months |
$ 150,000.00 |
|
|
363310 - Lubricants |
12 Months |
$ 300,000.00 |
|
|
239973 - Emergency Food Packs (Composit Ration Packs) |
12 Months |
$ 600,262.00 |
1 |
|
Sea container |
12 Months |
$ 735,000.00 |
|
|
674330 - Warehouse Management |
12 Months |
$ 1,989,600.00 |
3 |
|
333700 - Diesel fuel for generators |
12 Months |
$ 2,000,000.00 |
|
|
492216 - Refrigerated Containers |
12 Months |
$ 2,480,383.56 |
3 |
|
333700 - Diesel fuel for vehicles |
12 Months |
$ 4,500,000.00 |
|
|
333700 - Charcoal |
12 Months |
$ 7,500,000.00 |
|
|
931200 - Food Supply (Contingents Food Rations) |
12 Months |
$20,890,957.50 |
3 |
| Transport |
Light Vehicles |
55 |
$ 153,000.00 |
1-4 |
|
Escort |
1 |
$ 300,000.00 |
|
|
Lease |
4 |
$ 400,000.00 |
1-4 |
|
Shuttle and After Hours |
20 |
$ 400,000.00 |
1-4 |
|
MHE/ENGR PLANT/VEHICLES |
|
$ 444,600.00 |
1-4 |
|
B6 GP Heavy |
6 |
$ 460,000.00 |
4 |
|
MHE, Eng. Plant, vehicles |
|
$ 1,031,900.00 |
1-4 |
|